Big Dalton Dam Sluiceway Rehabilitation
-
Project Scope:This project will rehabilitate and upgrade the sluiceway; install new gates and valves; and recoat the existing valves, penstocks, and debris racks. This project will also upgrade the water, electrical, and valve control systems, construct a new reservoir access road, and place overhead utility lines underground.
-
Project Benefits:Improves flood management, storm water capture for more sustainable local water supply, and operational reliability at the dam
-
Community Engagement:N/A
-
Project Location:Big Dalton Dam in the City of Glendora
-
Cost Estimate:N/A
-
Economic Impact:N/A
-
Schedule:- Advertise for Construction – Aug 2019
- Start of Construction – Apr 2020
- End of Construction – Apr 2022