Project No. 530 Los Nietos, Line D, Sorensen Lateral

  • Project Scope:
    Construction of 407 linear feet of 30-inch reinforced concrete pipe lateral drain and two catch basins along Sorensen Avenue, east of Lambert Road. Construction of a new catch basin at the Mines Boulevard cul-de-sac south of the Mines Boulevard and Kengard Avenue intersection.
  • Project Benefits:
    Flood Risk Reduction Community Enhancement
  • Community Engagement:
    Project Information Flyers were mailed on Nov. 9, 2020 to over 100 residents in the immediate vicinity of the project.
  • Project Location:
    Sorensen Avenue and Lambert Road in the unincorporated community of West Whittier/Los Nietos.
  • Cost Estimate:
    - Total Project: $1,310,000 - Construction: $630,000
  • Economic Impact:
    Project construction supports 8 direct and indirect jobs.
  • Schedule:
    - Advertise for Construction – Aug 2021
    - Start of Construction – Mar 2022
    - End of Construction – Nov 2022
Please contact us with any questions about this project.
Haitham Ali, Project Manager
Office: (626) 458-3110