Alamitos Barrier Project Unit 15 Replacement Wells
-
Project Scope:Project will construct 5 new injection wells and 2 observation wells to replace and supplement existing ABP facilities. o 5 injection wells will be constructed to replace 4 existing injection wells that are beyond their useful life and require immediate replacement. Public Works will meet with representatives from local cities to inform and solicit input from the public on the project.
-
Project Benefits:Once the new injection wells are brought online, they will help prevent seawater intrusion by creating a freshwater pressure ridge in the underlying aquifers of the Central Basin located in the County of Los Angeles and the Coastal Plain of Orange County. The new observation well facilities will provide Public Works with valuable groundwater elevation and chloride concentration data to enable better operation of the ABP.
-
Community Engagement:A virtual community meeting was conducted with the Leisure World Community in the City of Seal Beach on June 29, 2021.
-
Project Location:Alamitos Barrier Project (ABP) facilities are located within the Cities of Long Beach and Seal Beach.
-
Cost Estimate:- Total Project: $8,400,000
-
Economic Impact:- Overall industry production value: $14,300,000 - Labor income: $4,600,000 - No. of jobs created: 43.6
-
Schedule:- Advertise for Construction – Nov 2021
- Start of Construction – Jun 2022
- End of Construction – Sep 2023
Please contact us with any questions about this project.
Chandra McLoud, Project Manager
Office: (626) 458-3165
cmcloud@dpw.lacounty.gov