Project No. 9408, West Hollywood - Pan Pacific Retention Basin Diversion Gate And Control House Upgrade
-
Project Scope:Replace existing slide gate, upgrade mechanical, electrical and control systems, and construct a new control house within the Pan Pacific Retention Basin.
-
Project Benefits:Improve operational reliability of the flood control house facility and the Pan Pacific Retention Basin.
-
Community Engagement:Flyers were provided during construction.
-
Project Location:It is located inside Pan Pacific Park across from The Grove Farmers Market (7600 Beverly Blvd, Los Angeles, CA 90036).
-
Cost Estimate:- Total Project: $7,900,000 - Construction: $4,400,000
-
Economic Impact:Project construction supports direct and indirect jobs.
-
Schedule:- Advertise for Construction – Aug 2021
- Start of Construction – Feb 2022
- End of Construction – Mar 2024
Please contact us with any questions about this project.
Cody Duncan, Project Manager
Office: (626) 658-0135