Naples Island Pump Stations Rehabilitation - Phase II

  • Project Scope:
    The project involves the replacement and upgrade of the pumps, ventilation system, electronic control and monitoring system, communication system, and improvement of maintenance access.
  • Project Benefits:
    Provide reliable flood control in a high inundation risk community.
  • Community Engagement:
    Informational flyers were mailed in January 2025, and will attend local community meeting to discuss more.
  • Project Page:
    https://pw.lacounty.gov/projects/naples-island/
  • Project Location:
    Naples Island, Long Beach
  • Cost Estimate:
    - Total Project: $9,200,000
  • Economic Impact:
    Project construction supports direct and indirect jobs.
  • Schedule:
    - Final Plans – Aug 2024
    - Advertise for Construction Bids – Feb 2025
    - Start of Construction – Apr 2026

    Note - Dates subject to change