Naples Island Pump Stations Rehabilitation - Phase II
-
Project Scope:The project involves the replacement and upgrade of the pumps, ventilation system, electronic control and monitoring system, communication system, and improvement of maintenance access.
-
Project Benefits:Provide reliable flood control in a high inundation risk community.
-
Community Engagement:Informational flyers were mailed in January 2025, and will attend local community meeting to discuss more.
-
Project Page:https://pw.lacounty.gov/projects/naples-island/
-
Project Location:Naples Island, Long Beach
-
Cost Estimate:- Total Project: $9,200,000
-
Economic Impact:Project construction supports direct and indirect jobs.
-
Schedule:- Final Plans – Aug 2024
- Advertise for Construction Bids – Feb 2025
- Start of Construction – Apr 2026
Note - Dates subject to change