Central PHC DM Repairs

  • Project Scope:
    The project consists of deferred maintenance repairs to HVAC, electrical, elevator, plumbing, and fire protection systems, and site utilities. These repairs were identified as high-priority deficiencies in the Strategic Asset Management (SAM) database.
  • Project Benefits:
    This project will invest in public infrastructure that will improve County services and facilities for the residents of the County seeking healthcare assistance.
  • Community Engagement:
    No.
  • Project Location:
    241 N. Figueroa Street, Los Angeles, CA 90012
  • Cost Estimate:
    - Total Project: $26,800,000 - Construction: $23,700,000
  • Economic Impact:
    - Overall industry production value: $40,200,000 - Labor income: $12,800,000 - No. of jobs created: 122.9
  • Schedule:
    - Advertise for Construction – Sep 2020
    - End of Construction – Feb 2023

    Note - Dates subject to change

Please contact us with any questions about this project.
Dan Carter, Project Manager
Office: (626) 300-2343