Ladera Heights - Centinela Avenue et al
-
Project Scope:The primary objective of this project is to improve roadway along Centinela Avenue: - Road resurfacing. - Reconstruct curbs, gutters and sidewalk.
-
Project Benefits:Improves quality of life for residents and lessens wear and tear on vehicles.
-
Community Engagement:A construction brochure will be provided approximately two weeks prior to start of construction.
-
Project Location:Unincorporated County community of Ladera Heights, City of Los Angeles and Culver City - Centinela Ave from Green Valley Cir to La Tijera Blvd. - Centinela Av from SR90/Centinela Creek to W Jefferson Blvd.
-
Cost Estimate:- Total Project: $3,500,000 - Construction: $1,820,000
-
Economic Impact:Project construction supports 18 direct and indirect jobs.
-
Schedule:- Final Plans – Aug 2022
- Advertise for Construction Bids – Sep 2023
- Start of Construction – Mar 2024
Note - Dates subject to change
Please contact us with any questions about this project.
Joshua Rojo, Project Manager