Wilshire Boulevard et al
-
Project Scope:The primary objective of this project is to improve 2.3 miles of roadway. - Pavement resurfacing and reconstruction - Curb ramp improvements - Signals relocation and upgrade - Sidewalk improvements and driveways reconstruction - Cross gutter reconstruction - Manhole reconstruction and adjustments - Tree removal and tree planting
-
Project Benefits:Improves quality of life for residents and lessens wear and tear on vehicles; improves pedestrian access.
-
Community Engagement:A project information flyer and a construction brochure will be provided just after the project has been awarded and a week prior to start of construction, respectively.
-
Project Location:Unincorporated County area of West Los Angeles.
-
Cost Estimate:- Total Project: $9,600,000 - Construction: $4,700,000
-
Economic Impact:Project construction supports 58 direct and indirect jobs.
-
Schedule:- Final Plans – Spring 2024
- Advertise for Construction Bids – Summer 2025
- Start of Construction – Spring 2026
Note - Dates subject to change
Please contact us with any questions about this project.
Al Azhang, Project Manager
aazhang@dpw.lacounty.gov