  • Project Scope:
    The primary objective of this project is to reconstruct 5.7 miles of residential roads. The project includes: - Parkway improvements - Curb ramps upgrade - Roadway reconstruction
  • Project Benefits:
    This project will improve quality of life for residents and lessen wear and tear on vehicles. This project will also help to preserve natural resources by using recycled and in-place materials, resulting in cost savings and reduction in greenhouse gas, energy, and landfill deposition.
  • Community Engagement:
    The project will be presented to the community on March 16, 2020. A construction brochure will be provided approximately two weeks prior to start of construction.
  • Project Location:
    Various roadways within the Unincorporated Community of Hacienda Heights.
  • Cost Estimate:
    - Total Project: $6,400,000 - Construction: $5,233,000
  • Economic Impact:
    Project construction supports 65 direct and indirect jobs.
  • Schedule:
    - Advertise for Construction – Aug 2019
    - Start of Construction – May 2020
    - End of Construction – Feb 2021