Compton Bl et al - East Rancho Dominguez
-
Project Scope:The primary objective of this project is to resurface 2.8 miles of major roadways. The project includes the following proposed work: - Parkway improvements - Curb ramps upgrades - Pavement resurface - Stormwater quality improvement elements - Traffic safety enhancements
-
Project Benefits:Improve quality of life for residents, improve stormwater quality, and lessen wear and tear on the vehicles.
-
Community Engagement:A construction brochure will be provided approximately two weeks prior to start of construction.
-
Project Location:Various roadways within the Unincorporated Community of East Rancho Dominguez and the City of Compton.
-
Cost Estimate:- Total Project: $13,800,000 - Construction: $6,500,000
-
Economic Impact:Project construction supports 114 direct and indirect jobs.
-
Schedule:- Final Plans – Early 2025
- Advertise for Construction Bids – Spring 2025
- Start of Construction – Early 2026
Note - Dates subject to change
Please contact us with any questions about this project.
Sonia Alvarez, Project Manager