Windsor Hills - Southridge Avenue et al
-
Project Scope:The primary objective of this project is to reconstruct 1.1 miles of roadways. The project includes the following proposed work: - Parkway improvements - Curb ramps upgrades - Intersection safety improvement - Restriping and traffic loop restoration
-
Project Benefits:This project will improve quality of life for residents and lessen wear and tear on vehicles.
-
Community Engagement:Multiple community engagement meetings will be held during various phases of the project to provide updates and receive feedback from the local community.
-
Project Location:Various roadways within the Unincorporated Community of Windsor Hills.
-
Cost Estimate:- Total Project: $6,120,000.00 - Construction: $5,049,000.00
-
Economic Impact:Project construction supports 63 direct and indirect jobs.
-
Schedule:- Final Plans – Summer 2025
- Advertise for Construction Bids – Spring 2026
- Start of Construction – Early 2027
Note - Dates subject to change