Norwalk Bl and Whittier Bl Intersection Improvements
-
Project Scope:The primary objective of this project is to improve traffic flow through the intersection as identified in the SR-91/I-605/I-405 Hot Spots Arterial Intersection Study completed in 2012: - Lengthen the left-turn lanes at all four approaches to the intersection. - Provide a dedicated right-turn lane at both Whittier Boulevard approaches to the intersection. - Provide an additional southbound through-lane on Norwalk Boulevard.
-
Project Benefits:The project seeks to increase the capacity of the intersection in advance of Caltrans' planned widening of the I-605 freeway.
-
Community Engagement:A project information flyer and a pre-construction brochure will be provided just after the project has been awarded and a week prior to start of construction, respectively.
-
Project Location:Unincorporated County community of West Whittier-Los Nietos and the City of Whittier.
-
Cost Estimate:- Total Project: $ 3,200,000 - Construction: $ 1,630,000 - Grant Funds: $ 2,830,000
-
Economic Impact:N/A
-
Schedule:- Final Plans – Jan 2031
- Advertise for Construction Bids – Sep 2031
- Start of Construction – Apr 2032
Note - Dates subject to change
Please contact us with any questions about this project.
Nadeem Syed, Project Manager
nsyed@dpw.lacounty.gov