Bridge Preventive Maintenance Program - Group 25 Cities
-
Project Scope:Bridge Preventive Maintenance
-
Project Benefits:The proposed work includes preventive maintenance and minor repairs to 11 bridges. Preventive maintenance is a sustainable practice that offers a cost effective way to preserve, extend, and maximize the useful life of bridges.
-
Community Engagement:A pre-consruction brochure will be provided a week prior to the start of construction.
-
Project Location:Various bridges within the cities of Hawthorne, Gardena, Huntington Park, Los Angeles, Pico Rivera, Santa Fe Springs, Downey, Commerce, Santa Monica, Bell, and the surrounding unincorporated areas.
-
Cost Estimate:Total Project: $3.1 million Contract Cost: $2.1 million
-
Economic Impact:Project construction supports 14 direct and indirect jobs.
-
Schedule:- Final Plans – Spring 2024
- Advertise for Construction Bids – Summer 2028
- Start of Construction – Spring 2029
Note - Dates subject to change