PW Banner

Slauson Blue Line Station Intersection Improvements

  • Project Scope:
    The project consists of pedestrian access improvements at five intersections including curb extensions, curb ramp upgrades, sidewalk and driveway repairs, enhanced crosswalk and advanced vehicle stop striping.
  • Project Benefits:
    Provide better connectivity to the Slauson Station of the Metro Blue Line by improving pedestrian safety at five intersections.
  • Community Engagement:
    A community meeting was held on April 30, 2024, from 6:00 PM to 7:00 PM at: Florence Library 7807 Compton Ave Los Angeles, CA 90001
  • Project Location:
    Five intersections in the Unincorporated County community of Florence-Firestone: · Slauson Ave. and Hooper Ave. · Slauson Ave. and Compton Ave. · Compton Ave. and 60th St. · Slauson Ave. and Miramonte Blvd. · Slauson Ave. and Holmes Ave.
  • Cost Estimate:
    Total Project: $3,600,000 Construction Costs: $1,764,264 Grant Funds: $1,465,000 Fed ID: ATPL-5953(773)
  • Economic Impact:
    Project construction supports 14 direct and indirect jobs.
  • Schedule:
    - Advertise for Construction – Dec 2022
    - Start of Construction – Jun 2024
    - End of Construction – May 2025

    Note - Dates subject to change

Please contact us with any questions about this project.
Kal Lambaz, Project Manager
Office: (714) 599-3545
klambaz@dpw.lacounty.gov