Hacienda Heights - Hacienda Boulevard Phase I
-
Project Scope:The primary objective of this project is to resurface 2.4 miles of major roadways. The project includes the following proposed work: - Pavement resurface - Sidewalk repairs - Guardrail upgrade - Tree removals and tree planting
-
Project Benefits:This project will reduce road noise for residents and lessen wear and tear on vehicles.
-
Community Engagement:A flyer to alert residents and businesses to the project will be distributed in Fall 2025. Future engagement planning will be discussed with Supervisorial District 1 to ensure community needs are met.
-
Project Location:County Unincorporated Community of Hacienda Heights.
-
Cost Estimate:- Total Project: $6,339,302 - Construction: $4,448,000
-
Economic Impact:Project construction supports 35 direct and indirect jobs.
-
Schedule:- Final Plans – Fall 2025
- Advertise for Construction Bids – Summer 2026
- Start of Construction – Spring 2027
Note - Dates subject to change