PW Banner

Acton - Red Rover Mine Road

  • Project Scope:
    The primary objective of this project is to resurface 2.5 miles of a major rural road. The project includes the following proposed work: - Pavement resurface
  • Project Benefits:
    This project will reduce road noise for residents and lessen wear and tear on vehicles. This project will also help to preserve natural resources by using recycled and in-place materials, resulting in cost savings and reduction in greenhouse gas, energy, and landfill deposition.
  • Community Engagement:
    A project information flyer and a construction brochure will be provided just after the project has been awarded and a week prior to start of construction, respectively.
  • Project Location:
    The Unincorporated Community of Acton.
  • Cost Estimate:
    - Total Project: $920,000 - Construction: $705,000
  • Economic Impact:
    Project construction supports 9 direct and indirect jobs.
  • Schedule:
    - End of Construction – Jul 2022
Location Map
Map