Altadena - Altadena Dr and Washington Blvd Roadway Improvement
-
Project Scope:The primary objective of this project is to reconstruct 2.0 miles of major roadways. The project includes the following proposed work: - Parkway improvements - Curb ramps upgrades - Roadway reconstruction - Traffic signal modifications and associated striping modifications
-
Project Benefits:This project will improve quality of life for residents and lessen wear and tear on vehicles. This project will also help to preserve natural resources by using recycled and in-place materials, resulting in cost savings and reduction in greenhouse gas, energy, and landfill deposition.
-
Community Engagement:A project information flyer and a pre-construction brochure will be provided just after the project has been awarded and a week prior to start of construction, respectively.
-
Project Location:Various roadways within the unincorporated County community of Altadena.
-
Cost Estimate:- Total Project: $7,700,000 - Construction: $4,120,000
-
Economic Impact:Project construction supports 51 direct and indirect jobs.
-
Schedule:- Advertise for Construction – Nov 2023
- Start of Construction – May 2024
- End of Construction – Jun 2025
Note - Dates subject to change
Please contact us with any questions about this project.
Bhetsua Tinoco Lima, Project Manager