Marvin Braude Bike Path Realignment Near Dockweiler Beach

  • Project Scope:
    The objective of this project is to realign a 0.2-mile-long existing bike trail to be away from the ocean because it was severely damaged as a result of the January 2023 storms. This portion of the trail has been closed since the storms.
  • Project Benefits:
    Realignment of the bike path away from the ocean will protect the bike path from future storm events.
  • Community Engagement:
    N/A
  • Project Location:
    Marvin Braude Bike Path from 950' South of Napoleon Street to Napoleon Street.
  • Cost Estimate:
    - Total Project: $1,000,000 - Construction: $700,000
  • Economic Impact:
    Project construction supports 4 direct and indirect jobs.
  • Schedule:
    - Final Plans – Feb 2024
    - Advertise for Construction Bids – Jan 2025
    - Start of Construction – Apr 2025

    Note - Dates subject to change

Please contact us with any questions about this project.
Rafael Ruiz, Project Manager