Project Scope:The primary objective of this project is to preserve 14 miles of rural roads. The project includes the following proposed work: - Pavement prep-work - Pavement preservation
-
Project Benefits:The proposed work includes micro-milling to improve road ride-ability; scrub seal to seal cracks; and slurry seal to preserve the pavement and provide a smoother, more finished driving surface. The preservation is estimated to extend the pavement life for an additional 6 to 8 years. To better care for the environment, all aggregates (tiny rocks) used come from recycled pavement.
-
Community Engagement:A project information flyer and a construction brochure will be provided just after the project has been awarded and a week prior to start of construction, respectively.
-
Project Location:Various roadways within the Unincorporated Community of Acton.
-
Cost Estimate:- Total Project: $3,200,000 - Construction: $2,600,000
-
Economic Impact:- Overall industry production value: $4,500,000 - Labor income: $1,500,000 - No. of jobs created: 13.5
-
Schedule:- Start of Construction – May 2023
- End of Construction – Jun 2023