Acton - Crown Valley Road, et al.

  • Project Scope:
    The primary objective of this project is to preserve 14 miles of rural roads. The project includes the following proposed work: - Pavement prep-work - Pavement preservation
  • Project Benefits:
    The proposed work includes micro-milling to improve road ride-ability; scrub seal to seal cracks; and slurry seal to preserve the pavement and provide a smoother, more finished driving surface. The preservation is estimated to extend the pavement life for an additional 6 to 8 years. To better care for the environment, all aggregates (tiny rocks) used come from recycled pavement.
  • Community Engagement:
    A project information flyer and a construction brochure will be provided just after the project has been awarded and a week prior to start of construction, respectively.
  • Project Location:
    Various roadways within the Unincorporated Community of Acton.
  • Cost Estimate:
    - Total Project: $3,200,000 - Construction: $2,600,000
  • Economic Impact:
    - Overall industry production value: $4,500,000 - Labor income: $1,500,000 - No. of jobs created: 13.5
  • Schedule:
    - Start of Construction – May 2023
    - End of Construction – Jun 2023
Location Map
Map