Project Scope:The primary objective of this project is to resurface 1.5 miles of local roadway. This project includes the following proposed work: 2" Mill and Pave.
-
Project Benefits:This project will reduce road noise for residents and lesson wear and tear on vehicles. This project will also help to preserve natural resources by using recycled and in-place materials, resulting in cost savings and reduction in greenhouse gas, energy, and landfill deposition.
-
Community Engagement:A project information flyer and a construction brochure will be provided a week prior to start of construction.
-
Project Location:Unincorporated Community of Littlerock.
-
Cost Estimate:- Total Project: $800,000 - Construction: $520,000
-
Economic Impact:Project construction supports direct and indirect jobs.
-
Schedule:- Start of Construction – Oct 2024
- End of Construction – Nov 2024