Monte Nido - Malibu Canyon Rd 1050 ft NO Malibu Crest Dr to Piuma Rd
-
Project Scope:Install curve advisory signs in accordance with current California Manual on Uniform Traffic Control Devices requirements to enhance safety along Malibu Canyon Rd from 1050ft N/O Malibu Crest Dr to Piuma Rd. The project will update existing signing along the road including installing advance curve advisory speed signs and arrows for horizontal curves where applicable.
-
Project Benefits:This signing project will enhance motorists' awareness of approaching curves in the roadway and the advisory speeds at which negotiating the curves are recommended.
-
Community Engagement:A project information flyer and a pre-construction brochure will be provided shortly after the project has been awarded and prior to start of construction.
-
Project Location:This project is located in the County of Los Angeles unincorporated community of Monte Nido. The length of the entire project is approximately 3.5 miles.
-
Cost Estimate:- Total Project: $400,000 - Construction: $164,730
-
Economic Impact:Project construction supports 2 direct and indirect jobs.
-
Schedule:- Final Plans – Sep 2023
- Advertise for Construction Bids – Jan 2026
- Start of Construction – Jul 2026
Note - Dates subject to change
Please contact us with any questions about this project.
Vince Jones, Project Manager
Office: (909) 238-8306
vjones@dpw.lacounty.gov
Location Map