Santa Monica Mountains - Stunt Rd btw Mulholland Hwy and Schueren Rd
-
Project Scope:Install both recessed transverse rumble strips and optical speed bars on Stunt Road to reduce vehicular speeds. Additionally, evaluate and update curve warning signs as needed.
-
Project Benefits:Slow down traffic on Stunt Road and potentially reduce traffic collisions
-
Community Engagement:Project was initiated at the request of the 3rd Supervisorial District Office and numerous constituents. Staff reached out to constituents when study was completed.
-
Project Location:The project is on Stunt Road between Mulholland Highway and Schueren Road, in the unincorporated community of Santa Monica Mountains in the Third Supervisorial District.
-
Cost Estimate:Total: $122,000 Construction: $45,000
-
Economic Impact:Project construction supports 0 direct and indirect jobs.
-
Schedule:- Final Plans – Fall 2025
- Start of Construction – Fall 2025
Note - Dates subject to change
Location Map