Hacienda Heights - Paso Verde Dr btw Haliburton Rd and Santa Bianca Dr
-
Project Scope:The objective of this project is to install speed cushions on Paso Verde Drive between Halliburton Road and Santa Bianca Drive.
-
Project Benefits:Reduce vehicular speeds on residential roadway.
-
Community Engagement:At the request of a constituent, Public Works conducted a study to determine the feasibility of installing speed cushions on Paso Verde Drive between Halliburton Road and Santa Bianca Drive.
-
Project Location:The project is on Paso Verde Drive between Halliburton Road and Santa Bianca Drive. Unincorporated Community of Hacienda Heights First Supervisorial District, RD 116 Thomas Guide Page 678-(D4)
-
Cost Estimate:Construction: $13,000
-
Economic Impact:Project construction supports 0 direct and indirect jobs.
-
Schedule:- Start of Construction – Mar 2024
- End of Construction – Mar 2024