Acton - Wisconsin St btw Sacramento Ave and Soledad Canyon Rd

  • Project Scope:
    The objective of this project is to install approximately 200 feet of double solid yellow centerline striping on Wisconsin Street between Sacramento Avenue and approximately 240 feet north of Soledad Canyon Road and install edge line striping on both sides of Wisconsin Street between Sacramento Avenue and Soledad Canyon Road.
  • Project Benefits:
    Double solid yellow centerline striping and edge line striping is intended to enhance traffic flow along Wisconsin Street.
  • Community Engagement:
    At the request of the former principal of Meadowlark Elementary School, Public Works conducted a study to determine how to help in easing traffic congestion during pick-up and drop-off times on Sacramento Avenue, west of Wisconsin Street and Wisconsin Street, south of Sacramento Avenue. Public Works will notify the requester and Supervisor Kathrin Barger's office prior to the installation.
  • Project Location:
    Supervisorial District: 5 Road Maintenance District: MD5 Flood Maintenance District: West Road Division: 557 Thomas Guide: 4465-C1 4465-C2 City: Unincorporated Community: Acton
  • Cost Estimate:
    Total: $16,000 Construction: $10,000
  • Economic Impact:
    Project construction supports 0 direct and indirect jobs.
  • Schedule:
    - Final Plans – Late 2025

    Note - Dates subject to change