Prairie Avenue TSSP - 118th Street to Redondo Beach Boulevard
-
Project Scope:The primary objective of the Prairie Avenue from 118th Street to Redondo Beach Boulevard Traffic Signal Synchronization Project is to improve the movement of vehicles and decrease the amount of time motorists will be stopping at red traffic signals. The project will o Upgrade 4 traffic signals o Timing and signal improvements o Place vehicle detectors in the pavement to detect the presence of vehicles o Synchronize traffic signals along the route by coordinating and adjusting the timing of signals between successive intersections
-
Project Benefits:This project will significantly reduce delays and accidents, thereby alleviating motorists' frustration, air pollution and operational costs.
-
Community Engagement:Community engagement will be conducted as appropriate.
-
Project Location:Communities of El Camino Village and the Cities of Hawthorne, Lawndale and Torrance.
-
Cost Estimate:- Total Project: $1,574,000.00
-
Economic Impact:Project construction supports 6.40 direct and indirect jobs.
-
Schedule:- Advertise for Construction – Dec 2022
- Start of Construction – Aug 2023
- End of Construction – Dec 2023
Please contact us with any questions about this project.
Khosrow Benyamin, Project Manager
Office: (310) 435-6161