Gateway Cities Fiber Optic Communications and CCTV Camera Project
  • Project Scope:
    The primary objective is to upgrade the City of South Gate's traffic signal communications and to create a Fiber Optic backbone network from the County's traffic signals west of Alameda Street through the cities of South Gate and Downey. Communications will be installed along: o Firestone Boulevard from Alameda Street to Ryerson Avenue; o Otis Street from Firestone Boulevard to South Gate City Yard; o Installation of 3 CCTV Cameras at various locations.
  • Project Benefits:
    This project will enhance the Intelligent Transportation Systems
  • Community Engagement:
    Community engagement will be conducted as appropriate including flyers and notices before construction.
  • Project Location:
    Communities of Cities of South Gate and Downey
  • Cost Estimate:
    $3,700,000.00
  • Economic Impact:
    Project construction supports 14.88 direct and indirect jobs.
  • Schedule:
    - Final Plans – Fall 2024
    - Advertise for Construction Bids – Summer 2025
    - Start of Construction – Spring 2026

    Note - Dates subject to change

Please contact us with any questions about this project.
Fedrico Hormozi, Project Manager