Big Dalton Spreading Grounds Improvement and Multi-Use Project
-
Project Scope:The Project proposes to improve the operability and storage capacity of the spreading grounds, improve the existing diversion structure to the spreading grounds from Big Dalton Debris Dam, install a pipeline for imported water between PM-26 and Big Dalton Spreading Grounds, and provide multi-use (recreational) amenities.
-
Project Benefits:The Project will improve operability and water conservation capacity of the Big Dalton Spreading Grounds. Current estimates anticipate an increase in 1,370 acre-feet of water conserved per average water-year.
-
Community Engagement:An agreement between TVMWD, the City of Glendora, and the LACFCD defining the responsibilities of each agency, including cost-sharing, will be negotiated and drafted once the Project Concept is approved.
-
Project Location:Big Dalton Spreading Grounds is located downstream of Big Dalton Debris Basin, between the Little Dalton Diversion Channel and Big Dalton Wash in the City of Glendora.
-
Cost Estimate:- Total Project Cost: $5,460,000 - Total Grant Amount: $2,160,000
-
Economic Impact:N/A
-
Schedule:- Final Plans – Fall 2022
- Advertise for Construction Bids – Early 2022
Note - Dates subject to change
Please contact us with any questions about this project.
Jonpaul Sarro, Project Manager
Office: (626) 570-2836
jsarro@dpw.lacounty.gov
Location Map