Project Summary
Public Works is collaborating with the City of Pasadena to evaluate and implement striping improvements at the intersection of Woodbury Road and Santa Rosa Avenue, which crosses jurisdictional boundaries between the two agencies.
The proposed improvements include an all-way stop control, painted crosswalks, traffic delineators, and pavement striping and markings. These improvements will increase pedestrian safety by promoting a clear and marked passageway across the intersection.
Resources
Project Schedule
Approval of plans by City and County: October 2023
Installation of stop signs and striping improvements: December 2023
Contacts
Kirk Torossian, Project Lead
ktorossian@pw.lacounty.gov
(626) 300-4795