Road Projects

Current Projects

PROJECT NAME SCOPE OF WORK PROJECT SUMMARY START DATE FINISH DATE
110 TH STREET DRAIN - BUDLONG AVENUE ROAD RESURFACING AND INTERSECTION RECONSTRUCTION RMD3267112 7/23/02 8/6/02
Hazard Av et al Road reconstruction, curb and gutter, curb ramps, cross gutters, sidewalk, driveways and bus pads; and the performance of other appurtenant work. RDC0016052 5/9/24 1/8/25
East Los Angeles - Cesar E Chavez Avenue The proposed work includes cold-mill and overlay with a layer of asphalt rubberized asphalt concrete to preserve and provide a long lasting finished driving surface. Needed sidewalk, curb, and gutter repair, traffic signal upgrades as well as installation of curb ramps will also be performed. RMD4102001 3/8/24 12/30/24
Altadena - Altadena Dr and Washington Blvd Roadway Improvement The proposed work includes cold-milling the existing pavement; pulverize the underlying base material and/or soil to produce pulverized base (PBM); and place a layer of rubberized hot-mix asphalt over the AC on PBM to provide a long-lasting finished driving surface. RMD2504001 5/6/24 9/12/25
U.S. 101/Palo Comado Canyon Rd Interchange Improvement (ABO)(AGH) Widen existing overcrossing from 40-feet to 76-feet to accommodate one travel lane in each direction, left-turn pockets, bike lanes, shoulders; and sidewalks. In addition, a signal will be installed at the northbound off-ramp to improve safety and circulation. RDC0016341 8/31/18 7/31/20
East Los Angeles Community Roadway Improvement Construction of curb and gutter, sidewalk, curb ramps, cross gutters, drainage structures, asphalt rubber and aggregate membrane, and tire rubber modified asphalt concrete; installation of striping and pavement markings; modification of traffic signals; and the performance of other appurtenant work. RDC0016147 8/7/23 10/28/24
Ladera Heights - Centinela Avenue et al The proposed work includes cold mill asphalt concrete pavement, asphalt rubber hot mix, PCC driveways, cross gutters, and curb ramps, bus pad, sidewalks, manhole reconstruction and adjustment, traffic control, signage and striping, bioswale with landscaping. RDC0012971 3/15/24 11/21/24
Walnut Park - Walnut Street et al The proposed work includes cold-mill enough existing pavement to produce cold central planted recycled pavement (CCPR); pulverize and stabilize the remaining existing pavement with the underlying base material and/or soil to produce cement stabilized pulverized base (CSPB); and place a layer of rubberized hot-mix asphalt over the CCPR on CSPB to provide a long-lasting finished driving surface. A Community meeting was held on October 17, 2023, and the construction brochure was delivered. RMD4108001 11/27/23 11/1/24
Colima Rd - City of Whittier Boundary to Fullerton Rd Pavement preservation, road widening, new bike lanes, traffic signal upgrades, landscaping and roadway improvements. RDC0014911 2/18/25 2/16/28


Future Projects

PROJECT NAME SCOPE OF WORK PROJECT SUMMARY START DATE FINISH DATE
Hacienda Heights - Hacienda Boulevard Phase I Road resurfacing including sidewalk reconstruction, guardrail upgrade, tree removals and tree planting. RMD1402001 8/22/25 4/8/26
Compton Bl et al - East Rancho Dominguez Resurface 2.0 miles of major roadways including parkway improvements and curb ramp upgrades. RDC0015726 8/25/25 5/17/27
Chatsworth - Lake Manor Drive et al reconstruction of roadway pavement using cold central plant recycled asphalt concrete pavement; construction of sidewalk, driveways, curb and gutter, curb ramps, and cross gutters; installation of striping and pavement markings; and the performance of other appurtenant work RMD3508001 12/30/25 10/9/26
Brea Canyon Cutoff Road, et al. The proposed work includes cold-mill existing pavement and overlay with a layer of tire rubber modified asphalt concrete to provide a long lasting finished driving surface. As needed sidewalk, curb, gutter, driveway, curb ramp upgrades, guardrail improvements, and traffic signal upgrades. RMD1403001 1/14/26 4/20/27
Rosewood - 139th Street, et al. Phase II The proposed work includes cold-mill enough existing pavement to produce cold central planted recycled pavement (CCPR); pulverize and stabilize the remaining existing pavement with the underlying base material and/or soil to produce cement stabilized pulverized base (CSPB); and place a layer of rubberized hot-mix asphalt over the CCPR on CSPB to provide a long lasting finished driving surface. RMD3208002 3/13/25 11/13/25
West Puente Valley - Temple Avenue et al The proposed work includes cold-mill and overlay with a layer of asphalt rubberized asphalt concrete to preserve and provide a long lasting finished driving surface. Needed sidewalk, curb, and gutter repair as well as installation of curb ramps will also be performed. RMD1102001 7/17/25 8/18/26
Wilshire Boulevard et al Reconstruction of curb & gutter, sidewalk, driveways, cross gutters, and curb ramps; construction of an asphalt-rubber and aggregate membrane, concrete pavement, and drainage structures, resurfacing of existing roadway pavement with tire rubber modified asphalt concrete; traffic signal modifications; installation of striping and pavement markings; and the performance of other appurtenant work. RDC0015533 12/30/25 5/28/27
Hacienda Heights Community - Leticia Drive et al Phase II Roadway reconstruction RMD1408001 10/3/25 5/13/26
East Los Angeles - Whiteside Street et al Ph I The proposed work includes pulverize and stabilize the remaining existing pavement with the underlying base material and/or soil to produce cement stabilized pulverized base (CSPB); and place a layer of rubberized hot-mix asphalt over the conventional asphalt on CSPB to provide a long lasting finished driving surface. Additionally, a storm drain will capture stormwater at the top of the hill of Buhler Circle and will convey it to existing catch-basins on Dodds Street. RDC0015913 4/30/25 4/17/26
Windsor Hills - Southridge Avenue et al The proposed work includes reconstruction of roadways, new bulbouts, needed sidewalk and driveways, curb, and gutter repair as well as installation of curb ramps, signing striping, traffic loop restoration will also be performed. RDC0015774 2/3/26 1/14/28
Avocado Heights San Jose Hills - Valley Boulevard Construction of tire rubber modified asphalt concrete and cold central plant recycled asphalt concrete pavement on cement stabilized pulverized base; reconstruction of curb and gutter, sidewalk, driveways, and curb ramps on crushed miscellaneous base material; striping and pavement markings; and the performance of other appurtenant work. RMD1104001 7/30/25 2/26/27
Washington Bl et al Road Resurfacing RDC0016075 3/19/26 11/19/26
Norwalk Bl et al Reconstruct and Resurface RDC0015912 6/22/26 4/14/28


Completed Projects

PROJECT NAME SCOPE OF WORK PROJECT SUMMARY START DATE FINISH DATE
South Antelope Valley - 10th Street East, et al. The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. RMD5508002 7/10/23 7/12/24
Del Sur - 90th St West - Ave G to Ave J Cold mill 2" asphalt pavement and put back 2" overlay RMD5502039 5/8/23
Altadena - Canyon Crest Rd: 2900' W/O Lincoln Av to Canyon Dell Dr Mill 1.5" of pavement and construct 1.5" of AC overlay RMD2506011 7/17/23 8/9/23
10th Street East - Avenue G / Avenue E The proposed work includes chip sealing to extend the road surface life. RMD55AT006 9/20/22
Kagel Canyon Road, et al. (Phase III) The proposed work includes dig-outs, cold-milling and paving of asphalt concrete to preserve and provide a long-lasting finished driving surface. RMD2505010 6/27/23
Altadena - Altadena Dr: Allen Av to 150' N/O Canyon Close Rd Mill 1.5" of pavement and construct 1.5" of AC overlay RMD2506012 8/28/23 9/1/23
Agua Dulce - Sierra Highway (Phase III) - Davenport Road to Center Street The proposed work includes cold mill existing pavement; cold-in-place recycling of roadway pavement; and place a layer of rubberized hot-mix asphalt over the CIR to provide a long lasting finished driving surface. Needed sidewalk, curb, and gutter repair as well as installation of curb ramps will also be performed. RMD2503002 5/12/23
Castaic/Lake Hughes - Ridge Route Rd -Pine Crest Pl to 4752 n/o Templin Hy Mill and pave approximately 7.37 miles RMD2502021 5/31/24
Sunnybrook Ln. Et Al Pavement preservation - Local Streets RMD4405012 9/30/22
South Antelope Valley - Sierra Highway from Pearblossom Highway to Avenue S The proposed work includes cold mill existing pavement; cold-in-place recycling of roadway pavement; and place a layer of rubberized hot-mix asphalt over the CIR to provide a long lasting finished driving surface. RMD5502018 6/12/23 10/20/23
Avenue G-6 - Division Street / 5th Street East The proposed work includes chip sealing to extend the road surface life. RMD55AT002 10/3/22
Del Sur - 110th Street West - Avenue F to Avenue J The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. RMD5502031 4/10/23 5/26/23
West Carson - Milton Street, et al. Reconstruction of roadway pavement using cold central plant recycled asphalt concrete pavement; construction of sidewalk, driveways, curb and gutter, curb ramps, and cross gutters; installation of striping and pavement markings; and the performance of other appurtenant work RMD3205003 8/19/22
Palmdale - Avenue P - 1674 E 20th St East to 30th St East The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. RMD5502041 11/6/23 6/1/24
Avenue J - 240th Street East / 255th Street East The proposed work involves chip sealing to extend the road surface life. RMD55AT005 11/22/22
230th Street East - Avenue G / Avenue D-9 The proposed work includes double chip sealing to extend the road surface life. RMD55AT004 11/22/22
Acton - Crown Valley Road Phase I Resurfacing 11.5 lane miles in the unincorporated community of Acton. RMD5502043 10/10/23 10/18/23
100th Street East - Avenue J / Avenue J-8; Avenue K / Avenue L The proposed work includes chip sealing to extend the road surface life. RMD55AT003 10/4/22
Leona Valley - Johnson Road - Elizabeth Lake Rd to Avenue J Cold mill 2" of asphalt and put back 2" overlay RMD5502038 6/30/23
Roosevelt - 60th Street East - Avenue E to Avenue I The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. RMD5506004 5/21/24
Windsor Hills - La Cienega Blvd Resurfacing The proposed work includes cold-mill and overlay with a layer of asphalt rubberized asphalt concrete to preserve and provide a long lasting finished driving surface. RMD3202005 5/31/23
Big Tujunga Canyon Road The proposed work includes cold mill existing pavement; cold-in-place recycling of roadway pavement; and place a layer of rubberized hot-mix asphalt over the CIR to provide a long lasting finished driving surface. Needed sidewalk, curb, and gutter repair as well as installation of curb ramps will also be performed. RMD5504003 8/5/22
Lake Los Angeles - Avenue H Scrub seal, Overlay RMD55AT010 6/7/24
Roosevelt - 70th Street East - Avenue E to Avenue I The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. RMD5502045 7/8/24 7/27/24
Lake Los Angeles - Avenue G Micro Milling, leveling course, 3/8" Chip RMD55AT009 8/8/24