|
Road Projects
Current Projects
PROJECT NAME |
SCOPE OF WORK |
PROJECT SUMMARY |
START DATE |
FINISH DATE |
110 TH STREET DRAIN - BUDLONG AVENUE |
ROAD RESURFACING AND INTERSECTION RECONSTRUCTION |
RMD3267112 |
7/23/02 |
8/6/02 |
Hazard Av et al |
Road reconstruction, curb and gutter, curb ramps, cross gutters, sidewalk, driveways and bus pads; and the performance of other appurtenant work. |
RDC0016052 |
5/9/24 |
1/8/25 |
East Los Angeles - Cesar E Chavez Avenue |
The proposed work includes cold-mill and overlay with a layer of asphalt rubberized asphalt concrete to preserve and provide a long lasting finished driving surface. Needed sidewalk, curb, and gutter repair, traffic signal upgrades as well as installation of curb ramps will also be performed. |
RMD4102001 |
3/8/24 |
12/30/24 |
Altadena - Altadena Dr and Washington Blvd Roadway Improvement |
The proposed work includes cold-milling the existing pavement; pulverize the underlying base material and/or soil to produce pulverized base (PBM); and place a layer of rubberized hot-mix asphalt over the AC on PBM to provide a long-lasting finished driving surface. |
RMD2504001 |
5/6/24 |
9/12/25 |
U.S. 101/Palo Comado Canyon Rd Interchange Improvement (ABO)(AGH) |
Widen existing overcrossing from 40-feet to 76-feet to accommodate one travel lane in each direction, left-turn pockets, bike lanes, shoulders; and sidewalks. In addition, a signal will be installed at the northbound off-ramp to improve safety and circulation. |
RDC0016341 |
8/31/18 |
7/31/20 |
East Los Angeles Community Roadway Improvement |
Construction of curb and gutter, sidewalk, curb ramps, cross gutters, drainage structures, asphalt rubber and aggregate membrane, and tire rubber modified asphalt concrete; installation of striping and pavement markings; modification of traffic signals; and the performance of other appurtenant work. |
RDC0016147 |
8/7/23 |
10/28/24 |
Ladera Heights - Centinela Avenue et al |
The proposed work includes cold mill asphalt concrete pavement, asphalt rubber hot mix, PCC driveways, cross gutters, and curb ramps, bus pad, sidewalks, manhole reconstruction and adjustment, traffic control, signage and striping, bioswale with landscaping. |
RDC0012971 |
3/15/24 |
11/21/24 |
Walnut Park - Walnut Street et al |
The proposed work includes cold-mill enough existing pavement to produce cold central planted recycled pavement (CCPR); pulverize and stabilize the remaining existing pavement with the underlying base material and/or soil to produce cement stabilized pulverized base (CSPB); and place a layer of rubberized hot-mix asphalt over the CCPR on CSPB to provide a long-lasting finished driving surface. A Community meeting was held on October 17, 2023, and the construction brochure was delivered. |
RMD4108001 |
11/27/23 |
11/1/24 |
Colima Rd - City of Whittier Boundary to Fullerton Rd |
Pavement preservation, road widening, new bike lanes, traffic signal upgrades, landscaping and roadway improvements. |
RDC0014911 |
2/18/25 |
2/16/28 |
Future Projects
PROJECT NAME |
SCOPE OF WORK |
PROJECT SUMMARY |
START DATE |
FINISH DATE |
Hacienda Heights - Hacienda Boulevard Phase I |
Road resurfacing including sidewalk reconstruction, guardrail upgrade, tree removals and tree planting. |
RMD1402001 |
8/22/25 |
4/8/26 |
Compton Bl et al - East Rancho Dominguez |
Resurface 2.0 miles of major roadways including parkway improvements and curb ramp upgrades. |
RDC0015726 |
8/25/25 |
5/17/27 |
Chatsworth - Lake Manor Drive et al |
reconstruction of roadway pavement using cold central plant recycled asphalt concrete pavement; construction of sidewalk, driveways, curb and gutter, curb ramps, and cross gutters; installation of striping and pavement markings; and the performance of other appurtenant work |
RMD3508001 |
12/30/25 |
10/9/26 |
Brea Canyon Cutoff Road, et al. |
The proposed work includes cold-mill existing pavement and overlay with a layer of tire rubber modified asphalt concrete to provide a long lasting finished driving surface. As needed sidewalk, curb, gutter, driveway, curb ramp upgrades, guardrail improvements, and traffic signal upgrades. |
RMD1403001 |
1/14/26 |
4/20/27 |
Rosewood - 139th Street, et al. Phase II |
The proposed work includes cold-mill enough existing pavement to produce cold central planted recycled pavement (CCPR); pulverize and stabilize the remaining existing pavement with the underlying base material and/or soil to produce cement stabilized pulverized base (CSPB); and place a layer of rubberized hot-mix asphalt over the CCPR on CSPB to provide a long lasting finished driving surface. |
RMD3208002 |
3/13/25 |
11/13/25 |
West Puente Valley - Temple Avenue et al |
The proposed work includes cold-mill and overlay with a layer of asphalt rubberized asphalt concrete to preserve and provide a long lasting finished driving surface. Needed sidewalk, curb, and gutter repair as well as installation of curb ramps will also be performed. |
RMD1102001 |
7/17/25 |
8/18/26 |
Wilshire Boulevard et al |
Reconstruction of curb & gutter, sidewalk, driveways, cross gutters, and curb ramps; construction of an asphalt-rubber and aggregate membrane, concrete pavement, and drainage structures, resurfacing of existing roadway pavement with tire rubber modified asphalt concrete; traffic signal modifications; installation of striping and pavement markings; and the performance of other appurtenant work. |
RDC0015533 |
12/30/25 |
5/28/27 |
Hacienda Heights Community - Leticia Drive et al Phase II |
Roadway reconstruction |
RMD1408001 |
10/3/25 |
5/13/26 |
East Los Angeles - Whiteside Street et al Ph I |
The proposed work includes pulverize and stabilize the remaining existing pavement with the underlying base material and/or soil to produce cement stabilized pulverized base (CSPB); and place a layer of rubberized hot-mix asphalt over the conventional asphalt on CSPB to provide a long lasting finished driving surface. Additionally, a storm drain will capture stormwater at the top of the hill of Buhler Circle and will convey it to existing catch-basins on Dodds Street. |
RDC0015913 |
4/30/25 |
4/17/26 |
Windsor Hills - Southridge Avenue et al |
The proposed work includes reconstruction of roadways, new bulbouts, needed sidewalk and driveways, curb, and gutter repair as well as installation of curb ramps, signing striping, traffic loop restoration will also be performed. |
RDC0015774 |
2/3/26 |
1/14/28 |
Avocado Heights San Jose Hills - Valley Boulevard |
Construction of tire rubber modified asphalt concrete and cold central plant recycled asphalt concrete pavement on cement stabilized pulverized base; reconstruction of curb and gutter, sidewalk, driveways, and curb ramps on crushed miscellaneous base material; striping and pavement markings; and the performance of other appurtenant work. |
RMD1104001 |
7/30/25 |
2/26/27 |
Washington Bl et al |
Road Resurfacing |
RDC0016075 |
3/19/26 |
11/19/26 |
Norwalk Bl et al |
Reconstruct and Resurface |
RDC0015912 |
6/22/26 |
4/14/28 |
Completed Projects
PROJECT NAME |
SCOPE OF WORK |
PROJECT SUMMARY |
START DATE |
FINISH DATE |
South Antelope Valley - 10th Street East, et al. |
The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. |
RMD5508002 |
7/10/23 |
7/12/24 |
Del Sur - 90th St West - Ave G to Ave J |
Cold mill 2" asphalt pavement and put back 2" overlay |
RMD5502039 |
|
5/8/23 |
Altadena - Canyon Crest Rd: 2900' W/O Lincoln Av to Canyon Dell Dr |
Mill 1.5" of pavement and construct 1.5" of AC overlay |
RMD2506011 |
7/17/23 |
8/9/23 |
10th Street East - Avenue G / Avenue E |
The proposed work includes chip sealing to extend the road surface life. |
RMD55AT006 |
|
9/20/22 |
Kagel Canyon Road, et al. (Phase III) |
The proposed work includes dig-outs, cold-milling and paving of asphalt concrete to preserve and provide a long-lasting finished driving surface. |
RMD2505010 |
|
6/27/23 |
Altadena - Altadena Dr: Allen Av to 150' N/O Canyon Close Rd |
Mill 1.5" of pavement and construct 1.5" of AC overlay |
RMD2506012 |
8/28/23 |
9/1/23 |
Agua Dulce - Sierra Highway (Phase III) - Davenport Road to Center Street |
The proposed work includes cold mill existing pavement; cold-in-place recycling of roadway pavement; and place a layer of rubberized hot-mix asphalt over the CIR to provide a long lasting finished driving surface. Needed sidewalk, curb, and gutter repair as well as installation of curb ramps will also be performed. |
RMD2503002 |
|
5/12/23 |
Castaic/Lake Hughes - Ridge Route Rd -Pine Crest Pl to 4752 n/o Templin Hy |
Mill and pave approximately 7.37 miles |
RMD2502021 |
|
5/31/24 |
Sunnybrook Ln. Et Al |
Pavement preservation - Local Streets |
RMD4405012 |
|
9/30/22 |
South Antelope Valley - Sierra Highway from Pearblossom Highway to Avenue S |
The proposed work includes cold mill existing pavement; cold-in-place recycling of roadway pavement; and place a layer of rubberized hot-mix asphalt over the CIR to provide a long lasting finished driving surface. |
RMD5502018 |
6/12/23 |
10/20/23 |
Avenue G-6 - Division Street / 5th Street East |
The proposed work includes chip sealing to extend the road surface life. |
RMD55AT002 |
|
10/3/22 |
Del Sur - 110th Street West - Avenue F to Avenue J |
The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. |
RMD5502031 |
4/10/23 |
5/26/23 |
West Carson - Milton Street, et al. |
Reconstruction of roadway pavement using cold central plant recycled asphalt concrete pavement; construction of sidewalk, driveways, curb and gutter, curb ramps, and cross gutters; installation of striping and pavement markings; and the performance of other appurtenant work |
RMD3205003 |
|
8/19/22 |
Palmdale - Avenue P - 1674 E 20th St East to 30th St East |
The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. |
RMD5502041 |
11/6/23 |
6/1/24 |
Avenue J - 240th Street East / 255th Street East |
The proposed work involves chip sealing to extend the road surface life. |
RMD55AT005 |
|
11/22/22 |
230th Street East - Avenue G / Avenue D-9 |
The proposed work includes double chip sealing to extend the road surface life. |
RMD55AT004 |
|
11/22/22 |
Acton - Crown Valley Road Phase I |
Resurfacing 11.5 lane miles in the unincorporated community of Acton. |
RMD5502043 |
10/10/23 |
10/18/23 |
100th Street East - Avenue J / Avenue J-8; Avenue K / Avenue L |
The proposed work includes chip sealing to extend the road surface life. |
RMD55AT003 |
|
10/4/22 |
Leona Valley - Johnson Road - Elizabeth Lake Rd to Avenue J |
Cold mill 2" of asphalt and put back 2" overlay |
RMD5502038 |
|
6/30/23 |
Roosevelt - 60th Street East - Avenue E to Avenue I |
The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. |
RMD5506004 |
|
5/21/24 |
Windsor Hills - La Cienega Blvd Resurfacing |
The proposed work includes cold-mill and overlay with a layer of asphalt rubberized asphalt concrete to preserve and provide a long lasting finished driving surface. |
RMD3202005 |
|
5/31/23 |
Big Tujunga Canyon Road |
The proposed work includes cold mill existing pavement; cold-in-place recycling of roadway pavement; and place a layer of rubberized hot-mix asphalt over the CIR to provide a long lasting finished driving surface. Needed sidewalk, curb, and gutter repair as well as installation of curb ramps will also be performed. |
RMD5504003 |
|
8/5/22 |
Lake Los Angeles - Avenue H |
Scrub seal, Overlay |
RMD55AT010 |
|
6/7/24 |
Roosevelt - 70th Street East - Avenue E to Avenue I |
The proposed work includes cold mill and overlay of AC pavement; installation of striping and pavement markings; and the performance of other appurtenant work. |
RMD5502045 |
7/8/24 |
7/27/24 |
Lake Los Angeles - Avenue G |
Micro Milling, leveling course, 3/8" Chip |
RMD55AT009 |
|
8/8/24 |
|