Rehabilitate Pavements for the South Taxi Lanes and Ramp Areas [Design]
The project includes the design for the rehabilitation of approximately 18 acres of pavements for the south aircraft parking ramp/apron area and taxi lanes. The estimated cost for design is $300,000.
Current Status:
- Received FAA Airport Improvement Grant in the amount of $300,388
- Design work to begin April/May 2026
- Construction planned for 2028; estimated to cost $1.3 million