ON THIS PAGE
General Wm. J. Fox Airfield Projects
Overview
Following are descriptions of projects currently underway at the airport. Please direct any questions or requests for more information to Samuel Maghakian, Project Manager at (626) 300-4615 or smaghakian@dpw.lacounty.gov.
Rehabilitate Pavements for the South Taxi Lanes J, D, and C and East Aircraft Parking Ramp/Apron and Between Hangar Rows [Design]
The project includes the design for the reconstruction of approximately 10 acres of pavements for taxi lanes J, D, and C, in between hangar rows E200-J900, and the east ramp/apron area. The estimated cost for design is $620,000.
Current Status:
- Received FAA Airport Improvement Grant in the amount of $589,433
- Received Caltrans Airport Improvement Program matching grant of $29,472
- Design work planned to begin March 2026
- Construction planned for 2029; estimated to cost $10,550,000
Contractor/Consultant Opportunities: None